Title
Authorizing the revision of lines and grades on City Plan Nos. 286 and 288 in the vicinity of Glengarry Road and St. Andrew Road, under certain terms and conditions.
Body
THE COUNCIL OF THE CITY OF PHILADELPHIA HEREBY ORDAINS:
SECTION 1. Pursuant to Section 11-405 of The Philadelphia Code, the Board of Surveyors of the Department of Streets is authorized to revise the lines and grades on City Plan Nos. 286 and 288 by:
(a) Striking from City Plan Nos. 286 and 288 Glengarry Road from St. Andrew Road to a dead end turnaround southwardly therefrom.
(b) Placing on the City Plan a right-of-way for drainage purposes and water main purposes and public utility purposes within the lines of Glengarry Road being stricken from the City Plan under authority of this Ordinance.
SECTION 2. This authorization is conditional upon compliance with the following requirements within one (1) year from the date this Ordinance becomes law:
(a) The party requesting changes to the City Plan hereunder shall file an agreement or agreements, satisfactory to the Law Department, executed by all owners of property affected by this Ordinance, to release the City from all damages and claims for damages that may arise by reason of such City Plan changes. If such requesting party has demonstrated to the satisfaction of the City that it has diligently pursued, but was unsuccessful in obtaining the execution of any such agreements, such party shall file agreements and bond with corporate surety, satisfactory to the Law Department, to release and indemnify the City for all such damages and claims for damages.
(b) The party requesting changes to the City Plan hereunder shall file an agreement, satisfactory to the Law Department, to release, indemnify and defend the City from all damages or claims for damages, which may arise by reason of such City Plan changes.
(c) The party requesting changes to the City Plan hereunder shall file an agreement, satisfactory to the Law Department, to make any and all changes and adjustments to curbing, sidewalk paving, cartway paving, water pipe, fire hydrants, sewers, inlets and manholes, street light poles and equipment, and to other City structures either overhead, underground or upon the surface, including the relocation, abandonment, repairing, reconstruction, cutting and sealing of such structures and facilities which may be necessary in the judgment of the Department of Streets and Water Department by reason of the City Plan changes authorized herein. The agreement shall provide for the removal of all existing City-owned street lighting poles and equipment and for their delivery to the storage yard of the Street Lighting Division at 701 Ramona Avenue at no cost to the City. The agreement shall provide for the removal of salvageable hydrants, valves, manhole covers, frames and connections, as determined by the Water Department, and for their delivery to the storage yard of the Water Department located at Twenty-ninth Street and Cambria Street at no cost to the City. The agreement shall also provide for the removal of salvageable cast iron manholes and covers, street inlet grates, frames and hoods, and inlet castings, as determined by the Water Department, and for their delivery to the storage yard of the Water Department located at 3201 Fox Street at no cost to the City. The agreement shall provide that this work be completed within one year from the date of confirmation by the Board of Surveyors on the City Plan changes authorized by this Ordinance.
(d) The party requesting changes to the City Plan hereunder shall file a bond, with corporate surety, satisfactory to the Law Department, to cover the cost of work required under Section 2(c).
(e) The filing of an agreement by the owner or owners of property affected thereby granting to the City of Philadelphia the aforesaid right-of-way described in Section 1(b) of this Ordinance. The agreement shall provide that no changes in grades shall be made and that no fences, buildings or other structures, either overhead, underground or upon the surface shall be constructed within the lines of the right-of-way or abutting thereon, unless the plans for such structures shall first be submitted to and approved by the City of Philadelphia. The agreement shall also grant the right-of-access and occupation at any and all times to the officers, agents, employees and contractors of the City of Philadelphia to occupy the right-of-way for the purpose of construction, reconstruction, maintenance, alterations, repairs and inspection of present and future facilities and structures.
(f) The payment by the party in interest of the cost of advertising the public hearing by the Board of Surveyors on the City Plan changes authorized by this Ordinance.
SECTION 3. This Ordinance shall not become effective unless the sum of two hundred dollars ($200.00), toward costs thereof, is paid into the City Treasury within one hundred twenty (120) days after this Ordinance becomes law.
End