header-left
File #: 220947    Version: 0 Name:
Type: Bill Status: ENACTED
File created: 12/1/2022 In control: Committee on Streets and Services
On agenda: Final action: 3/30/2023
Title: Authorizing the paving of Frances Harper Drive from Passyunk Avenue to Penrose Avenue, Hartranft Street from 26th Street to Schuylkill Avenue, Schuylkill Avenue from Passyunk Avenue to Penrose Avenue, and an extension of Passyunk Avenue Service Road (aka Frontage Road) from its current terminus to Schuylkill Avenue, under certain terms and conditions.
Sponsors: Councilmember Johnson
Indexes: PAVING
Attachments: 1. L220947 - Exhibit, As Introduced.pdf, 2. Bill No. 22094700.pdf, 3. CertifiedCopy22094700
Title
Authorizing the paving of Frances Harper Drive from Passyunk Avenue to Penrose Avenue, Hartranft Street from 26th Street to Schuylkill Avenue, Schuylkill Avenue from Passyunk Avenue to Penrose Avenue, and an extension of Passyunk Avenue Service Road (aka Frontage Road) from its current terminus to Schuylkill Avenue, under certain terms and conditions.

Body
THE COUNCIL OF THE CITY OF PHILADELPHIA HEREBY ORDAINS:

SECTION 1. The Procurement Commissioner, pursuant to the provisions of Sections 11-502 and 11-503 of The Philadelphia Code, is hereby authorized to enter into a contract for the paving of Frances Harper Drive from Passyunk Avenue to Penrose Avenue, Hartranft Street from 26th Street to Schuylkill Avenue, Schuylkill Avenue from Passyunk Avenue to Penrose Avenue, and an extension of Passyunk Avenue Service Road (aka Frontage Road) from its current terminus as shown on City Plan to Schuylkill Avenue.

Subject to all other sections of this Ordinance, the locations of the roads to be paved, including, Frances Harper Drive, Hartranft Street, Schuylkill Avenue, and Passyunk Avenue Service Road (aka Frontage Road) are generally shown on the Proposed Street Plan, dated October 5, 2022, prepared by Pennoni Associates Inc., attached to this Ordinance as Exhibit "A" and incorporated herein by this reference.

SECTION 2. In lieu of the provisions of Section 1, the party in interest shall file an agreement and bond with corporate surety, satisfactory to the City Solicitor and in an amount determined by the Streets Department, to cover the cost of the work required to completely pave the said Frances Harper Drive, Hartranft Street, Schuylkill Avenue, and Passyunk Avenue Service Road (aka Frontage Road), at its sole cost and expense in accordance with the specifications and requirements of the City of Philadelphia.

SECTION 3. No contract or agreement pursuant to Sections 1 and 2 of this Ordinance for the paving work authorized herein shall be entered into unless ...

Click here for full text